Design
& Supply Contractor - HLD Ltd. Installation Contractor -
L&L Installations. Main Contractor - Geoffrey Osborne
Ltd. Softwood decking over softwood joists and posts.
Boardwalk approx 84m long with 11 turns and falls/rsies.
Works installed dry and site flooded upon completion.
Completion - February 2006
|